South Lawrence Columbia Gas Crisis Reconstruction Project

Newsletter-Banner

Background

On September 13, 2018, an over-pressurization of the the natural gas lines in the Merrimack Valley region resulted in a series of fires and explosions, and rendered the gas distribution system inoperable. Consequently, nearly 30 miles of underground gas piping was replaced in the City of Lawrence, resulting in major impacts to the City’s roadways and sidewalks. 

In the spring of 2019, Columbia Gas entered into an $80 million Settlement Agreement with the affected municipalities, in which funding was provided for the restoration of the affected roads and sidewalks. The share of funds designated for restoration in Lawrence amounted to $31.9 million.

Restoration Overview

The South Lawrence Roadway Restoration project will take place in four (4) phases, beginning in 2019, and is expected to be completed by the end of 2022. The below map highlights the roads included in the restoration project, and are color-coded by planned year of completion.

Some of the impacted roads also require utility (water, sewer, drainage) replacement. In those cases, they will be repaved on a separate schedule. Those road segments are shown in gray in the below map.

The work areas are generally described as follows:

  • 2019: Colonial Heights and Southeast Mount Vernon
  • 2020: Mount Vernon
  • 2021: South Lawrence East
  • 2022: Carletonville
Roadway Overview Map Opens in new windowPreliminary Restoration Paving Plan Map - September 2019

This map shows the roadways which will be paved as part of the Settlement Agreement, color-coded by calendar year. The figure is based on all data available to the City and its consultants as of the date of preparation.
City of Lawrence - Updated CIP Map Opens in new window**Updated** Restoration Paving Plan Map - June 2020

This updated map shows the roadways which will be paved as part of the Settlement Agreement, color-coded by calendar year. Updates to this version include denoting streets that have already been paved, as well as capturing any data previously missed. The figure is based on all data available to the City and its consultants as of the date of preparation.

Calendar Year 2020 Roadway Restoration Work

Work for Calendar Year 2020 (CY2020) will consist of several phases, including mill-and-overlay of sections of roadway in the Mount Vernon and Sacred Heart neighborhoods, and full sidewalk rehabilitation in the O’Connell South Common neighborhood. 

Some sections of road will require full-depth reclamation, which involves extensive excavation and rebuilding of the road from the bottom up. This process is very lengthy, but results in improved drainage and more pronounced sidewalks and curbs. 

While roadway work is being completed in the above areas, water and sewer pipes will be replaced in sections of the O’Connell South Common and Carletonville neighborhoods. This will allow the trenches to settle through at least one freeze-thaw cycle and ensure that the road does not sink or crack once the final paving is complete. 

The below color-coded map shows completed work in black, current work in orange, and future work in gray.

COL NEWSLETTER Page_1
COL NEWSLETTER Page_2
COL NEWSLETTER Page_3
COL NEWSLETTER Page_4
COL NEWSLETTER Page_5
COL NEWSLETTERPage_6
COL NEWSLETTER Page_7